Day 1, master builder Freddy going over the plan with his labour
End of day 1, foundations dug and laid
Day 2, up to floor level
Day 3, slab preparation and keying for doorway
Day 4, full swing getting to roof level and floor slab
Day 5, floor screed and truss extensions fitted. Roof level at last
Day 6, window borders and internal wall plastering
Day 7, roof sheets, internal wall skimming and laundry counter walls (to lay the granite counters on)
Kennedy putting a lick of paint. Also notice the new solar geyser (thanks Nige for your help), plumbing and paving from garage to laundry door!